Home / Featured / More Lift Bridge Closures Planned
Frank A. Douglass Insurance Agency

More Lift Bridge Closures Planned

Maintenance work will require more early morning traffic delays on the Houghton-Hancock Bridge this week.

Contractors will be closing the bridge multiple times between tomorrow morning and Friday morning. Closings will range from 25 to 40 minutes each. No more than four closures are planned for any one morning. Traffic will be restored by 5:15 each morning.

There may be additional single-lane closures, as well. 

The schedule is tentative, and may be adjusted depending on the weather.

The closures will allow the installation of lower buffers and the removal of the old lift motors, which could not be completed last week because of high winds.

Check Also

Hancock Plans to Hire a Worker for the Campground

Hancock’s campground brings many visitors to the city each year. The city of Hancock seeks to hire a campground …

[sam id="3" codes="true"]